The agency disabled all new units after technicians linked the nationwide flight chaos to a device in Arkansas, prompting a $50.1 billion funding request.

By Victoria Hayes ·

Illustration for: FAA halts Juniper router rollout after El Dorado failure
Illustration generated for this article, not a news photograph.

The Federal Aviation Administration paused the installation of new network routers on Friday after technicians identified a unit in El Dorado, Arkansas, as the source of last week's widespread flight disruptions. The agency simultaneously disabled the functionality of every existing Juniper router in its network.

FAA spokesperson Ian Gregor stated that the decision followed a finding that the El Dorado device had triggered the instability. He noted that a second router installed in Amarillo, Texas, three weeks prior, also experienced similar control issues. The agency is now relying on older Cisco routers that have operated for 25 years to keep the network running while the investigation continues.

The system overload occurred while a federal contractor replaced obsolete copper cables with fiber optic lines across the country. Transportation Secretary Sean Duffy said the airspace closure was necessary after the new L3Harris-installed router in Arkansas caused a cascade of communication and radar signal failures. The disruption affected 17 of the 22 regional air traffic control centers, which manage high-altitude flights.

FAA documents describe the failure as an influx of excessive data flooding the system at a rate of 1,000 connection attempts every four to five seconds. This surge created instability in aircraft communications and radar signals. The failed units are currently undergoing testing in a laboratory at L3Harris headquarters.

Hewlett Packard Enterprise, the owner of the Juniper brand, told ABC News that the routers performed as configured by the installer when the flights were suspended. A company statement read that the device did not fail or act improperly based on current knowledge. The company has not yet responded to inquiries from The Associated Press.

Senate Democrats on the Commerce Committee said they believe only 400 of the more than 3,600 new routers have been installed so far. In a letter to Secretary Duffy, they argued that identifying the failed device does not explain why it failed. The senators urged the FAA to determine the root cause and report to Congress on how it plans to prevent future issues.

The Trump administration sent a letter to key legislators on Tuesday detailing a request for $50.1 billion to modernize the aviation system. The proposal includes $10.1 billion specifically for updating air traffic control. The remaining funds would cover airport infrastructure, terminal renovations at high-impact centers, the construction of five new control centers, and upgrades to up to 140 FAA-owned control towers.

Congress approved $12.5 billion last year to modernize infrastructure supporting more than 45,000 daily flights. Those funds were designated to replace outdated technologies such as 1980s-era radars and floppy disks. Much of that money will also go toward runway improvements and other construction projects.

More News · Orlando news · Report a business · Got a Story?

Get Central Florida Herald in your inboxLocal news for Central Florida, Florida. Free, a few times a week, unsubscribe any time.

Get Central Florida Herald in your inboxLocal news for Central Florida, Florida. Free, a few times a week, unsubscribe any time.